Upcoming Events

No Calendar Events Found or Calendar not set to Public.

In the summer of 2012, all four teams had the opportunity to travel to their respective communities halfway around the world. Throughout the previous school year each team had focused on their community and prepared for the upcoming summer trip. Since each community had different needs, the summer trips varied from team to team.

 

Tacachia, Bolivia:

 

During the July 2012 trip, the team worked on a number of projects. The distribution team worked with the community to finish installing the water distribution system and fix any broken parts of the system. Also, the team assessed new potential water sources near the community of Tacachia, which consisted of a spring, a well, or a river. As part of this assessment the team completed some water treatment tests to see how they could improve drinking water quality. The ram pump team worked with community members to test and fix any problems to the previously installed ram pumps. The latrines team collected preliminary information on the future location and implementation of the latrines. The team worked with our in-country partner Engineers in Action (EIA) to implement an erosion control solution, consisting of digging a new path for the river to flow through and using this excavated dirt to armor the riverbanks. This solution will provide protection for the community’s farmland because the river is a cause of a large loss of farmland due to floods and mudflows each year. These improvements directly affect the members of the community and have an indirect positive impact on surrounding communities.

 

Los Eucaliptos, Bolivia (formerly known as Erquis Sud):

 

In May 2012, the team traveled to Bolivia with 14 students, 1 faculty member, and 1 professional mentor to build two projects and assess one project. The team added on to the existing erosion control system. One gabion spur, consisting of 2x1x1 meter mesh baskets filled with large rocks, was extended downstream to prevent erosion of the community’s land. 200 feet of steel water pipe were added between the location of the well, and the water tank was installed. The surface water control, or flooding, team held meetings with the community and other stakeholders to approve the location of the proposed flooding channels, which are designed to prevent the existing flooding within the community. In addition, negotiations were held with two separate well drilling companies.


Santiago, Honduras:

 

The Honduras team completed a host of projects during the 2012 implementation trip. The team hired a contractor to drill a well to increase water supply to the community. By the time the team left Honduras, the well was near completion. A contractor was also hired to build an elevated well house, which was designed by the team. In addition, the team received a fully up-to-date map of Santiago and was able to map out the entire community’s water distribution system. With the new map, the team worked alongside the community to conduct a leak study on a third of the system. They pinpointed leaks and measured the associated water loss. Lastly, the team constructed a water level indicator for the community’s storage tank. Before this tool, the water level could only be determined by climbing onto the tank and looking inside. Now anyone can easily read the water level, even from a distance.


Nahualate, Guatemala:

  

In August of 2012, a team of 8 students, 1 faculty advisor, and 1 professional mentor returned to Nahualate, Guatemala, on a technical assessment and implementation trip. During this implementation trip, the team moved the location of the well to allow easier access for the large drilling machinery. The drilling began as of August 8th, and the well is projected to be finished by November of 2012. The community’s water committee also met with the team to discuss areas where pipes were needed and started installing some of the piping. They also discussed the progress of the project and further plans for the future.

For the 2011 trips, all four teams traveled over the summer to build or maintain their designs in their respective countries. Most teams also took on a teaching role this year, teaching the communities to maintain and control their own projects when EWB leaves.

In May, the Tacachia, Bolivia team traveled and worked to finish several existing projects. The biosand team took surveys and spoke with each family about issues with the filters or their implementation to see how the filters could be improved upon. The community members dug the trenches for the main line of the water distribution system, and the distribution team completed two of the three branches of the main line and worked on a third. A community member was shown how to maintain and construct the system when the team leaves, so the third branch should be completed by the community. The ram pumps and galvanized steel delivery line were completed. The community was taught how to clean and maintain the pumps on their own in the future, and the erosion control team finished an extensive survey of the Rio Palca river and its banks, allowing for further design decisions to be made next year.

The Erquis Sud, Bolivia team traveled in July to begin work on an erosion control system, which will protect the eroding river bank from further damage. One wall of the gabion system was completed, a second was started, and two more should be completed during the dry season next year. The team also took extensive surveys of the area’s topography in order to assess the flooding damage and devise a solution.

The Santiago, Honduras team split into three sub-teams this year: tank, health and education, and water distribution. The tank team spent the trip improving and maintaining the community water tank by cleaning and sealing the 40,000 gallon tank and ensuring that it remains protected from environmental hazards in the next year. The health and education team collected data on the water consumption and overall wellness in the community, working with the local water committee and the community itself. The water distribution team surveyed the land for a location to build a new tank and assisted in collecting water-consumption data. They also built a 500 ft pipeline to provide water to the community of Almendros.

Finally, the Nahualate, Guatemala team traveled in August for assessment and implementation of last year’s designs .The team took topographic data of the community to finalize the pipeline design. With the help from the community, a well house was built to store and protect electrical equipment for the well. The well itself is currently being dug by a Guatemalan drilling company hired on the previous trip where work is continuing at a steady pace. The team met with the local water committee to keep them up to speed on the projects and discuss future plans for implementation next year.

2010 has been a busy year for EWB at Missouri S&T! At the beginning of the year, the Nahualate, Erquis Sud, and Tacachia Projects went on assessment trips to help finalize their designs for the summer. After a busy spring of finalizing design, the projects made final travel plans.

Read more: Summer 2010 Update

Find Us On FaceBook - Image
Follow Us On Twitter - Image

Tacachia, Bolivia

Missouri S&T students discuss their EWB experiences helping bring clean water to the village of Tacachia.

tacachia

Site Login